Wow
It’s encouraging to see the state governments committed to resolving the Cumbres & Toltec washout quickly, with a target of reopening by your Memorial Day 2027!
Meanwhile, our local heritage railway has been dealing with bridge safety problems identified as far back as 2019, including serious masonry defects and deteriorating structural components. Government funding was committed, yet years later, SteamRanger is still operating split services, with no clear resolution in sight.
Many of us here wish our government had shown the same urgency in preserving our railway heritage as it did in using public parklands to attract tourists through a 6 year commitment to motorsport and, more recently, the now-defunct LIV Golf. Perhaps then we might have seen our trains running along the entire line by now.
FYI: I had 315 backdated to the 1923 look as 425, as we had a Pete Lerro charter on the C&T just after the storms… The Charter had to be modified, cause we couldn’t run all the way across to Chama from Antonito, due to the damage. We ran just a ways past Osier for some bridge photo run bys. And turned and went back to Antonito. Very successful Charter.
We were scheduled to run a string of cars from Antonito over to Chama, and spend the winter in stall 1 of the old roundhouse, but with the line cut, we are now sleeping in Antonito for the winter.
We have a early season charter scheduled but we will see if the repairs can be completed in time, if not we would run an modified one on the East side and maybe on up to Cumbres pass and back to Antonito.
One of the issues is that the major damage is on the Chama to Cumbres side of the mountain, and the BIG diesel ( ex WP&Y) is trapped on the East side. it has been almost exclusively used for ROW work and balasting. Where now, to haul fill into the bad washout area, it could only work from the top of the pass, down 4% grade to the washout area, and all the fill would need to be hauled to the top of the pass first. There is no road access into the canyon where the big washout is…Cutting a road in might be the easiest way to access. That area can see 6-10 feet of snow accumulation in the winter, so work to place a huge culvert or two would need to get laid before winter sets in, or have to wit till the spring thaw in May.
The Durango & Silverton also sustained some damage as well.
I wonder if it would be worth hauling the diesel by road trailer to Chama before the work begins. Alternately, a transfer set up at the road crossing at Cumbres Pass would eliminate the need for the ballast train to climb that grade fully loaded.
Almost wish there were a way to send some of that water to Roanoke, VA. We have been experiencing drought conditions here.
Regards, David Meashey
Dave
I understand that the washout is not at the horseshoe curve but is at the next creek uphill where the next right hand curve is… If so the easiest way to get fill to that location is from Cumbres Pass. Getting heavy equipment into that area is not going to be easy.
Stan
Stan You are so right…
SORRY Guys… I did that at 11pm… Tired Eyes
Here is the correct location…
And for you that are not aquatinted with that part of the C&T, here is a Google Earth Street View looking at Windy Point and on up hill ( 4% grade) to Cumbres Pass.
Stan’s point about access is the key one: if fill has to come in from Cumbres Pass, a transfer at the highway crossing only helps if there is room to unload and turn equipment without blocking the road. Otherwise a short temporary haul road along the right-of-way may be more practical than bringing loaded ballast cars up the 4% grade. I’d want to know whether the washout is close enough to the pass for shuttle trucks or a conveyor to reach it.
Another Google Earth shot, with the washout area in the center.
Is the line intact (or readily repairable) from at least one direction to the washout? If not, yeah that looks like rough transport.
From the top of Cumbres Pass its right at 1 mile down the hill on the ROW. A 159’ drop.
From the Coxo crossing, it’s about 1.25 miles up hill, on the ROW. with a 196’ rise.
At the closest point from the road it’s only about 800 ft up the hill to the washout, But there is 180 feet vertical climb. That’s a 25% grade, 1 foot vertical for every 4 feet forward. That’s really steep for a loaded dump truck.
With the sheer rock ledge cut of Windy Point and another ledge cut a bit lower, I don’t think that there is clearance to cut a road on the ledge, with out going right over the tracks. It would take a lot of fill to be brought in just to protect the tracks…
Originally in 1881 there was ( until last week) a stone culvert built there, it was 4’ wide x 4’ tall and 153’ long, where the fill went over the top. So it will take yet another LARGE convert brought in and assembled before new fill can even be started…
EDIT: here is a link to a damage assessment report.
But I’m not in charge and not an engineer… we will see…
Thanks for posting that, Dave.
Very informing, but very saddening.
Such a devastating event.
Maybe the solution is to look backwards, not forwards. Build a wooden trestle to make the span to get the line back up and making money, Then back fill the trestle as was done in the OLD DAYS. Not elegant but quick to get the line open.
This approach will also give the back fill time to settle and stabilize before it becomes the road bed.
D&RGW “OB” is functional and 315/425 has powered it in the past. It was restored by the “Friends”… Now in what condition it would be to do hard daily work IDK. The biggest issue would be to put together a 'Bridge Crew" that would know what to do with it…And actually get work done. It is on the East Side…
Here is a short Video of it working… I’m the lead guy for the interface between the hookup of the two… I’m in the cab…